Agency guidance reviewed November 2026. Cover image is an illustration.
Before you rely on this guide. Rebuild rules can change. Confirm the current requirements for your address with the permitting agency before committing to a design.
Short answer. For qualifying January 2025 wildfire rebuilds, LADBS handles permits in Pacific Palisades within Los Angeles city limits. LA County handles permits in unincorporated Altadena. Start with the property address, pre-fire building records, and a sketch of the proposed changes.
Who issues your fire rebuild permit?
| Property | Where to start |
|---|---|
| City of Los Angeles, including Pacific Palisades properties inside city limits | Check the City’s recovery guidance and ask LADBS which program applies. City Planning’s Palisades rebuild FAQ |
| Unincorporated LA County, including Altadena | Confirm the County’s application path and what debris-clearance records are required. LA County rebuild permits |
| Other incorporated cities | Contact the permitting authority for the property to confirm local requirements and any recovery program. |
Like-for-like rebuilds in Pacific Palisades and Altadena
For the primary structure on a qualifying City project, Emergency Executive Order 1 compares the pre-fire building footprint and height, with a 110% cap on each. The primary structure must remain in substantially the same location, and the project must retain the pre-fire use. Certain prior zoning nonconformities may be retained. Emergency Executive Order 8 provides a separate pathway for qualifying zoning-compliant single-family rebuilds in affected coastal areas. Confirm the conditions for the address before assuming either path applies. LADBS EO 1 eligibility criteria · City Planning’s EO 8 guidelines
In unincorporated LA County, the County describes a 10% limit for qualifying modifications in the Palisades Fire area and 10% or 200 square feet, whichever is greater, in the Eaton Fire area. County guidance lists floor area, size, height and footprint. Ask the County how to apply its criteria to your plans. County like-for-like guidance
City example. A pre-fire house with a 1,500-square-foot footprint has a 1,650-square-foot footprint cap under EO 1. A 1,625-square-foot footprint meets that particular test. A 1,700-square-foot footprint exceeds it. Height, location, use and other eligibility conditions still apply.
What self-certification changes
The City’s pilot allows approved California-licensed architects or civil engineers to certify plans within the eligible program scope in place of a full conventional building plan check. LADBS can audit the plans. Required inspections and applicable outside clearances still apply. The County operates its own pilot for eligible projects, with its own registration and review conditions. LADBS self-certification · LADBS pilot guidelines · County self-certification pilot
Energy, wildfire construction, and fee rules
California Executive Order N-37-25, issued November 24, 2025, replaced the first two paragraphs of N-29-25. For qualifying residential projects involving structures substantially damaged or destroyed in the declared emergency, specified solar PV and battery installation requirements remain suspended. Applicable solar-ready requirements still apply. Qualifying projects may use the 2022 California Building Standards Code subject to the order’s exceptions, including specified 2025 fire and public-safety requirements and applicable flood-elevation standards. The order also treats certain increased costs as eligible for building-code upgrade coverage under the cited Insurance Code provisions. Homeowners should verify the terms and limits of their own policy. Governor’s order on wildfire rebuild energy and code requirements
LA County offers fee deferrals and has refund procedures for eligible owners and projects. Check the County’s criteria before assuming the project qualifies. LA County fee relief
The rebuild sequence
- Confirm the jurisdiction, site access, and debris-clearance status. The County accepts recovery permit applications before cleanup is complete and requires both debris-removal phases to be complete before issuing permits for the projects covered by its guidance.
- Gather pre-fire plans, permits, and footprint records. Ask what the agency accepts as proof of the prior structure.
- Compare the existing footprint and proposed design with the applicable program requirements. Confirm which surveys, soils reports, or grading reviews your property needs.
- Submit under the approved route with a qualified design team. Obtain the required clearances and permits before starting the covered construction.
- Plan utility reconnections, construction inspections, and applicable occupancy approval. County permit guidance · City Planning’s Palisades rebuild FAQ
Frequently asked questions
Can I keep my old foundation?
Under the City’s EO 1 guidelines, LADBS allows reuse of the existing slab and foundation if a California-licensed structural engineer or architect evaluates the foundation system and finds it in satisfactory condition. Submit the documentation to LADBS for review and approval. City implementation guidelines
Can I build a larger home?
It depends on the parcel, the prior structure, and the program. Bring the former and proposed height, footprint, and floor area to the agency before committing to drawings.
Does self-certification remove inspections?
Required construction inspections still apply, and the agency may review or audit plans under its program rules. LADBS pilot guidelines
Do I need to install solar panels on the rebuilt home?
Specified solar and battery installation requirements are suspended for qualifying rebuilds under N-37-25. Applicable solar-ready requirements remain in place. Ask the permitting agency to confirm that the project qualifies. Governor’s order updating the wildfire rebuild solar rules
See Cali Builders’ custom-home construction services and the Los Angeles hillside and fire-zone guide.
Related planning guides
For repairs to a damaged house, review our fire damage restoration services alongside the property-specific rebuilding requirements.